[2020.11] Share free CompTIA PK0-004 exam tips questions and PK0-004 dumps from Lead4pass

comptia pk0-004 tips

leads4pass has updated CompTIA PK0-004 dumps issues! The latest PK0-004 exam questions can help you pass the exam! All questions are corrected
to ensure authenticity and effectiveness! Download the leads4pass PK0-004 PDF (Total Questions: 437 Q&A PK0-004 Dumps)

CompTIA PK0-004 Practice testing questions from Youtbe

https://youtube.com/watch?v=xLFX9RNtgYg

Examscode Exam Table of Contents:

Latest CompTIA PK0-004 google drive

[Latest PDF] Free CompTIA PK0-004 pdf dumps download from Google Drive: https://drive.google.com/file/d/1GrK7qflbAeFaGkigX-BGkxQ0n3CAkjQc/

Share CompTIA PK0-004 exam questions for free

QUESTION 1
A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may
cause delivery delays.
Which of the following is the BEST risk response strategy?
A. Exploit
B. Enhance
C. Mitigate
D. Communicate
Correct Answer: C

QUESTION 2
A company\\’s management team is in a meeting to review all the products and services delivered in the first quarter of
the year for profitability. They are requesting information on payback period, return on investment, and total cost of
ownership. The project manager is checking the project repository for available documentation. In which of the following
documents is the project manager MOST likely to find the required information?
A. Business case
B. Project charter
C. Risk management plan
D. Scope of work
Correct Answer: A

QUESTION 3
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because
requirements continue to be identified as work packages are being delivered.
Which of the following are NOST likely missing from the project? (Select two.)
A. Project charter
B. Organizational chart
C. Scope document
D. Status report
E. Business case
F. Project plan
Correct Answer: CF

QUESTION 4
A company has hired a new project manager. The PMO has briefed the new project manager on the following expected
responsibilities for projects:
Coordinate project schedule
Manage to the triple constraint
Provide performance feedback to team members\\’ managers
Which of the following types of organizational structures did the new project manager MOST likely join?
A. Balanced matrix
B. Strong matrix
C. Functional
D. Projectized
Correct Answer: D

QUESTION 5
Which of the following are the roles involved in a Scrum project?
A. Scrum master, development team, quality coach
B. Scrum master, business analyst, product owner
C. Scrum master, product owner, development team
D. Scrum master, project sponsor, business analyst
Correct Answer: C

QUESTION 6
Due to a new government regulation, a project change is required. The project manager evaluates the change and
realizes a representative from the legal department will need to approve the change as well. The project manager
should:
A. follow the change process flow and notify the legal department after the change is implemented.
B. extend a formal invitation to the legal department representative to join the CCB.
C. hold a separate meeting with the legal department representative and ask for approval.
D. notify the legal department representative in the event of an upcoming audit.
Correct Answer: B
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294

QUESTION 7
A project team is defining detailed risks. Which of the following project phases is taking place?
A. Initiation
B. Monitor and control
C. Execution
D. Planning
Correct Answer: D

QUESTION 8
A governance committee has just approved a new project. The project scheduler is now developing the project
schedule. Which of the following activities should be done FIRST?
A. Add durations.
B. Add the start and finish dates
C. Add tasks.
D. Add resources.
Correct Answer: C

QUESTION 9
Which of the following charts is a graphical representation of the causes of a specific event?
A. Histogram
B. Scatter
C. Fishbone
D. Gantt
Correct Answer: C
A fishbone diagram is a cause-and-effect diagram that shows the relationship between the effects of problems and their
causes. This diagram depicts every potential cause of a problem and the effect that each proposed solution will have on
the problem.

QUESTION 10
At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the
reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?
A. Project charter, organization chart, scope statement, and issue log
B. Dashboard information, action items, project schedule, and status report
C. Project management plan, scope statement, communication plan, and meeting agendas
D. Project schedule, project management plan, communication plan, and issue log
Correct Answer: A

QUESTION 11
A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel
decides to house a different type of reptile that will require a different temperature range than the capacity of the
installed system. The modification has been approved.
Which of the following constraints are MOST likely to be affected? (Choose two.)
A. Quality because the existing system is now outside the threshold.
B. Requirements because this is a change to initial scope.
C. Cost because replacing the system incurs additional expense.
D. Schedule because this was an unscheduled task and will impact the timeline.
E. Stakeholders because they will need to understand the modification and provide buy-in.
Correct Answer: CD
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293

QUESTION 12
Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future
event on an entity outside the organization?
A. Risk avoidance:e
B. Risk transfer
C. Risk exploitation
D. Risk mitigation
Correct Answer: B

QUESTION 13
An active project has a CPI of 0.92. Which of the following can be determined?
A. The project is currently over budget.
B. The project has a budget surplus.
C. The project is ahead of schedule.
D. The project is behind schedule.
Correct Answer: A
Reference http://smallbusiness.chron.com/project-management-cpi-numbers-mean-35541.html

Latest leads4pass CompTIA dumps Discount Code 2020

leads4pass coupon 2020

About The leads4pass Dumps Advantage

leads4pass has 7 years of exam experience! A number of professional CompTIA exam experts! Update exam questions throughout the year! The most complete exam questions and answers! The safest buying experience! The greatest free sharing of exam practice questions and answers!
Our goal is to help more people pass the CompTIA exam! Exams are a part of life, but they are important!
In the study you need to sum up the study! Trust leads4pass to help you pass the exam 100%!
why leads4pass

Summarize:

This blog shares the latest CompTIA PK0-004 exam dumps, PK0-004 exam questions and answers! PK0-004 pdf, PK0-004 exam video!
You can also practice the test online! leads4pass is the industry leader!
Select leads4pass PK0-004 exams Pass CompTIA PK0-004 exams “CompTIA Project +”. Help you successfully pass the PK0-004 exam.

ps.

Latest update leads4pass PK0-004 exam dumps: https://www.leads4pass.com/pk0-004.html (437 Q&As)
[Q1-Q12 PDF] Free CompTIA PK0-004 pdf dumps download from Google Drive: https://drive.google.com/file/d/1GrK7qflbAeFaGkigX-BGkxQ0n3CAkjQc/